Phase 2 · Module 1 · Backlog and start

Early week 2, a 90-minute workshop: the backlog table of 8–15 instructions, with one named owner per entry.

Updated · GIRI 12.80.1

Without a backlog, the loudest voice decides each week, and after 5 weeks 30 instructions are started and none is finished. The backlog is your contract document and your sales tool: when the plant manager asks “What are you actually doing?”, you open one page.

8–15entries
1name per entry
1page for management

The workshop: 90 minutes, 5 steps

  1. Define the area (15 min). “Packaging line 2”, not “all of production”. One line done fully beats five done halfway.
  2. Get 5–8 candidates into the table (30 min). Per entry: task, use case, today’s problem, value. 8 sketched beat 3 perfect.
  3. One named person per entry (20 min). Not “the shift”. Plus a backlog lead who keeps the whole thing in view.
  4. Plan how to inform the team (15 min). 5 minutes per shift, three sentences are enough.
  5. KPI estimates (10 min). Baseline and target where measurable. Where not: the value in words. Invent nothing.

What a backlog looks like: example

Task Owner Target
CNC mill · Standard tool change Mia Wagner Set-up time 30 → 20 min
CNC mill · Clear fault E-42 Mia Wagner Downtime −20 min per case
Assembly · Daily cleaning Lea Schmidt fully documented
Goods-in · Labelling variant X Tom Becker Halve the error rate
Hall A · Forklift visual check Alex Berger every check verifiable
A folder for your area, here “Line 3 / Test station”
A folder for your area, here “Line 3 / Test station”

Homework by the end of week 2 (~3 hrs)

  • Sharpen the backlog to 8–15 entries.
  • Measure baselines: time set-ups with a stopwatch, ask for scrap rates.
  • Inform all shifts.
  • Start the first 1–2 recordings. Don’t wait for a perfect backlog.
  • For module 2: list your 6 stakeholders.